A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.

A heavy industrial design firm has over US$3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.
What is the most effective method to capture these opportunities?
A. Integrate them into the RBS.
B. Schedule a project team meeting.
C. Formally notify the project manager.
D. Establish a contingency reserve.