What is the best reason for the duplicate risk identification sessions?

You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning.
What is the best reason for the duplicate risk identification sessions?
A. The iterative meetings allow the project manager and the risk identification participants to identify newlydiscovered risk events throughout the project.
B. The iterative meetings allow all stakeholders to participate in the risk identification processes throughout theproject phases.
C. The iterative meetings allow the project manager to discuss the risk events which have passed the projectand which did not happen.
D. The iterative meetings allow the project manager to communicate pending risks events during projectexecution.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.