Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed.
What recommendation could be implemented to prevent this from recurring?
A. Use the Monte Carlo simulation.
B. Implement a reserve analysis process.
C. Conduct more frequent reserve watch list status meetings.
D. Increase the contingency reserve.