A project risk manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the communication style may be the main contributor.

A project risk manager is concerned about the low performance of risk management on a mission-critical project. After assessing the situation, the risk manager finds that the communication style may be the main contributor.
What could the project risk manager do to adjust the approach to influence team members to improve performance?

A. Use follow-up emails, adopt an open door policy, and ask for feedback
B. Seek hidden agendas, vent frustrations, and allow others to vent frustrations
C. Provide continuous support, counseling, build trust, and open communications
D. Conduct one-on-one meetings, more frequent follow-up meetings, and implement the management by walking around technique.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.