During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?
A. Project management plan, project documents, and human resource plan
B. Change requests, project management plan, and project documents
C. Change requests, cost plan, and project documents
D. Enterprise environmental factors, change requests, and project management plan
B. Change requests, project management plan, and project documents