What other information should the project manager update the risk register with?

As a part of monitoring and controlling the project, the project manager should update the risk register. The project manager should update the risk register with information on risk reassessment, risk audits, and periodic risk reviews. What other information should the project manager update the risk register with?
A. Actual costs and schedule delays of risk events.
B. Actual outcomes of risk management duties by the project team.
C. Actual cost of risk events.
D. Actual outcomes of the project’s risks and of the risk responses.