What is the best source of project information which could result in the reduction of risk?

What is the best source of project information which could result in the reduction of risk?
A. Determine the risks by using brainstorming techniques.
B. Sensitivity analysis.
C. Review organizational process assets, lessons learned from previous projects similar in nature.
D. Make observations/conversations on the current projects.