What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identification?

Frank is the project manager of the NHL Project for his company and he is starting the risk ActualTests.com identification process for the project. Frank needs to ensure that the correct stakeholders are interviewed as part of risk identification. What document will help Frank to communicate and solicit inputs of the project stakeholders during risk identification?
A. Project charter
B. Risk register
C. Requirements management plan
D. Stakeholder register