The stakeholder is unwilling to make decisions that would result in negative consequences to the project. Which of the following describes the stakeholders attitude regarding project risks?
A. Risk averse
B. Risk neutral
C. Risk accepting
D. Not enough information available to describe the stakeholder’s risk attitude.