What component of the change control system communicates the approval or denial of a proposed change request?

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
A. Configuration management system
B. Scope change control system
C. Integrated change control
D. Change log