Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the risk manager do first?
A. Meet with the project team.
B. Inform management of out-of-scope work.
C. Review activities for new risks.
D. Review the change control log.