Home » PMI » PMI-RMP » A risk manager works with the project team, senior management team, subject matter experts and other stakeholders to identify the project risks. Which of the following tools/methods from the risk management plan can be used to identify a risk, which is based on project objectives by category?
A risk manager works with the project team, senior management team, subject matter experts and other stakeholders to identify the project risks. Which of the following tools/methods from the risk management plan can be used to identify a risk, which is based on project objectives by category?
A. Affinity diagram
B. Risk breakdown structure
C. Decision tree method
D. Work breakdown structure
Correct Answer: C
Explanation/Reference: