There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will
NOT help you, the project manager, to prepare for risk monitoring and controlling?
A. Work Performance Information
B. Project management plan
C. Risk register
D. Change requests
I think A and D are not correct as both of them are output of Risk Monitoring and Controlling.
Work Performance Date is Input..