A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.

A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.
What risk related information should be included in the monthly status meeting of this complex project?
A. Top priority risks at present, risks closed in the last period, milestone changes
B. Top priority risks at present, risks that have occurred, risk management plan
C. Top priority risks at present, risks that have occurred, changes in scope
D. Top priority risks at present, risks that have occurred, risks closed in the last period

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.