Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5.
A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfall. What is the most effective way to explain the risk to this stakeholder?
A. The funding shortage is the lowest ranked/scored risk.
B. The funding shortage is a significant risk.
C. The funding shortage will have a very high impact on the project and is the highest priority.
D. The funding shortage has a very low probability of occurring and is not a concern for the project.