During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customers electrical infrastructure. This event was not originally identified as a risk. To maintain the project schedule, the project manager decides to purchase a new power adapter.
What type of response best describes this course of action?
A. Contingency plan
B. Management plan
C. Fallback plan
D. Workaround