A project in the execution phase at the customer’s site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.

A project in the execution phase at the customer’s site has an issue concerning new parts that do not fit properly into a machine. The site project manager cannot find this high probability risk in the risk register.
What action should the site project manager take?
A. Variance analysis
B. Workaround
C. Risk assessment
D. Risk audit