A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small.

A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small.
Would it be appropriate for the project manager to implement some level of risk management?
A. Yes, even small projects may require risk planning.
B. No, small projects do not usually require risk planning.
C. No, risk planning should be initiated with the sponsor’s consent.
D. Yes, the risk planning process implementation is ultimately the project manager’s decision.