As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?
A. Risk reserve analysis and risk thresholds
B. Risk response strategies and risk analysis
C. Risk reviews and risk register analysis
D. Risk assessments and risk audits