During a status meeting, a functional manager complains that the server backup failed, impacting the department. This was a known risk documented in the risk register as an accepted risk. After reviewing the meeting minutes, itis determined that the functional manager had not participated in the risk planning phase.
Which of the identification methods should have been applied?
A. Qualitative analysis
B. Sensitivity analysis
C. Stakeholder analysis
D. Quantitative analysis