Contingency Reserve Total: US$213,000
Due to a mitigation strategy, Risk 4’s probability has been reduced to 40%. What would be the new contingency reserve total?
A. US$92,400
B. US$145,800
C. US$157,000
D. Unable to calculate a total due to lack of pertinent information.