While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfil these newly discovered requirements.

While preparing for a project review meeting with leadership, the project team analyzes and checks its scope activities and discovers missing requirements. The project risk manager decides to hire a subcontractor to fulfil these newly discovered requirements.
What risk strategy did the project risk manager use?
A. Avoid
B. Transfer
C. Accept
D. Mitigate