What additional information can you associate with the identified risk events?

You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?
A. Risk potential responses
B. Risk schedule
C. Risk owner
D. Risk cost