Which of the following strategies will you use to tackle the risk?

You work as the project manager for BlueWell Inc. You are monitoring the project performance. You want to make a decision to change the project plan to eliminate a risk in order to protect the project objectives. Which of the following strategies will you use to tackle the risk?
A. Risk mitigation
B. Risk avoidance
C. Risk acceptance
D. Risk transference