The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?

The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?
A. Risk breakdown structure
B. Risk management plan
C. Risk register
D. Risk control plan