What project management process group will you implement risk response plans?

You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?
A. Executing
B. Planning
C. Monitoring and Controlling
D. In any process group where the risk event resides