To properly ensure risk information is incorporated into the overall project management framework, risk data must be provided to the schedule analysts and cost estimators on a periodic basis. How frequently should this be performed?
A. As defined in the risk plan
B. At least once per month
C. At the end of the financial quarter
D. As defined in the company standards