The team has just completed a risk response planning session and identified responses for all the high and medium priority risks. What should the team do with the remaining low priority risks?
A. Create risk responses later, as time allows.
B. Add the risks to a watchlist for periodic monitoring.
C. Remove the risks from the risk register.
D. Conduct a low priority risk response planning workshop with key stakeholders.