What type of risk response has been used in this instance?

Shawn is the project manager of the WHT Project for his company. In this project Shawn’s team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?
A. Avoidance
B. Exploiting
C. Accepting
D. Enhancing