A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance.

A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance.
Which aspect of risk impact is most important when designing the risk impact scale?
A. Technical performance
B. Cost
C. Technical requirements
D. Schedule

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.