What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?

You are the project manager of the HJU project for your company. This project will last for 18 months and has a project budget of $567,000. Robert, one of your stakeholders, has introduced a scope change request that will likely have an impact on the project costs and schedule. Robert assures you that he will pay for the extra time and costs associated with the risk event. You tell Robert that the change request may affect more areas of the project than just time and cost and that you are worried about the additional risks the change request will bring.
What project management component is responsible for evaluating a change request and its impact on all of the project management knowledge areas?
A. Project change control system
B. Integrated change control
C. Risk analysis
D. Configuration management

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.