How much detail and repetition in approach for risks to be reassessed for probability and impact?

Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment of risks within each project. How much detail and repetition in approach for risks to be reassessed for probability and impact?
A. Each risk reassessment should go into the same depth as the original risk assessment activity.
B. The probability and impact of risk event should determine the level of reassessment throughout the projectlifecycle.
C. The amount of detail of repetition that is appropriate depends on how the project progresses relative to itsobjectives.
D. The level of detail and reassessment should reflect the priority of the project.