The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:

The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
A. Risk 1
B. Risk 2
C. Risk 3
D. Risk 4

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.