After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.

After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.
What is the forecasting methodology that should be utilized to calculate the impact?
A. Estimate to complete (ETC)
B. Budget at completion (BAC)
C. Estimate risk completion (ERC)
D. Estimate at completion (EAC)