The company board is concerned about potential legal action from a high-risk project. What technique can be used to justify risk response decisions taken on this project?

The company board is concerned about potential legal action from a high-risk project. What technique can be used to justify risk response decisions taken on this project?
A. Interviews
B. Nominal group technique
C. Brainstorming
D. Decision tree analysis