Where can Mark determine the priority of a risk given its probability and impact?

Mark is the project manager of the BFL project for his organization. He and the project team are creating a probability and impact matrix using RAG rating. There is some confusion and disagreement among the project team as to how a certain risk is important and priority for attention should be managed. Where can Mark determine the priority of a risk given its probability and impact?
A. Risk management plan
B. Project sponsor
C. Risk response plan
D. Look-up table