A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations.
What risk information should be communicated to the project sponsor?
A. Significant risks and issues and their planned responses
B. Risk matrix showing the distribution of high, medium, and low risks
C. Results of the last project risk brainstorming session
D. Summary feedback from the previous risk audit