Home » PMI » PMI-RMP » A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?
A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?
A. Risk register
B. Risk response plan
C. Risk management plan
D. Risk identification plan
Correct Answer: C