What should Lamont do with the risk responses he identified during the project’s monitoring and controlling process?

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project’s monitoring and controlling process?
A. Include the risk response in the project risk management plan.
B. Include the responses in the project management plan.
C. Nothing. The risk responses are included in the project’s risk register already.
D. Include the risk responses in the organization’s lessons learned database.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.