The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a onemonth delay.
What should the project manager do next to reduce further delay?
A. Initiate a scope change request.
B. Schedule a project kick-off meeting.
C. Schedule a stakeholder meeting.
D. Engage the project sponsor/portfolio manager.