Why would the project manager need to update the WBS after the risk response planning process?

You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.
A. Because of work that was omitted during the WBS creation
B. Because of new work generated by the risk responses
C. Because of risk responses that are now activities
D. Because of risks associated with work packages