Which approach is the preferred method to address project risks and the risk responses?

Gary is the project manager of the MMQ project for his company. He is working with his project team to plan the risk responses for his project. Sarah, a project team member, does not understand the process that Gary is using to plan the risk responses. Which approach is the preferred method to address project risks and the risk responses?
A. Risks in the project should be addressed by their probability for creating risk responses.
B. Risks in the project should be addressed by the organization’s risk tolerance for creating risk responses.
C. Risks in the project should be addressed by their impact for creating risk responses.D. Risks in the project should be addressed by their priority for creating risk responses.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.