C. and Sam review the offer and agree that while their project may qualify for the discounted materials the savings is nominal and they would not necessarily pursue the savings. Lisa documents this positive risk response in the risk register. What risk response is this?
A. Enhance Transference
Share
D. Acceptance

Download Printable PDF. VALID exam to help you PASS.