A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation.
Where should the stakeholder look to determine the amount that can be approved?
A. Project charter
B. Risk management plan
C. Risk register
D. Organizational process assets