The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the project, and during the first status meeting an issue is identified.
What is the appropriate course of action in this case?
A. Perform a project review.
B. Perform a risk reserve analysis.
C. Implement an action plan to resolve the issue.
D. Delegate to the action owner.