There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to the perform quantitative risk analysis process?
A. Risk register
B. Risk management plan
C. Cost management plan
D. Enterprise environmental factors
agreed. these answers are about 30% incorrect.
This question is not correct. There are six inputs to “perform quantitative risk analysis” process:
1. Risk register
2. Risk management plan
3. Cost management plan
4. Schedule management plan
5. EEF
6. OPA