A teaming agreement is an example of what risk response?

You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
A. Transference
B. Acceptance
C. Mitigation
D. Sharing

Download Printable PDF. VALID exam to help you PASS.

2 thoughts on “A teaming agreement is an example of what risk response?

    1. There are 5 risk responses to positive risks (Opportunities) as per PMBOK 6
      * Exploit
      * Enhance
      * Share
      * Accept
      * Escalate

      Share strategy is applied for Teaming agreement