What risk response is David proposing to management?

David is the project manager of the NKL Project for his organization. He has been asked to create a proposal for a construction project for a client. David realizes that there are several requirements within the SOW and RFP provided by the client that would eliminate his company from bidding on the construction project. David proposed to management that his organization create a partnership with a competitor so that together they could bid on the construction project and qualify for the customer’s requirements. What risk response is David proposing to management?
A. Exploiting
B. Teaming agreement
C. Transference
D. Sharing