The project manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, but rather, should complete this at the beginning of the project.

The project manager schedules a third workshop to facilitate the qualitative risk analysis. One team member complains that they should not have iterative meetings, but rather, should complete this at the beginning of the project.
Which of the following should the project manager do?
A. Continue with the workshop, but discipline the team member for undermining the authority of the project manager.
B. Agree with the team member, as qualitative analysis should only be performed during the initial stages of a project.
C. Proceed with the meeting, but remove the team member from the invitees’ list.
D. Explain that itis good practice to perform qualitative analysis throughout the life of the project.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.