What diagramming technique are you using as a part of the risk identification process?

You are the project manager of RTF project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows causal factors for an effect to be solved. What diagramming technique are you using as a part of the risk identification process?
A. Cause and effect diagrams
B. System or process flow charts
C. Predecessor and successor diagramming
D. Influence diagrams